Quick check: first 5 mm interception storage compliance for any catchment.
Enter total site area and impermeable areas for S2 compliance calculation
Sites must provide 5mm of interception storage across all contributing SuDS components. This represents the daily rainfall that must be managed on-site for a typical UK location.
Required volume = Impermeable area (m²) × 0.005m (5mm)
Example: 85,000 m² × 0.005m = 425 m³
Add each SuDS component and calculate interception credit
| Component Type | Area Served (m²) | Component Area/Vol | Credit (%) | Interception (m³) | Action |
|---|
Permeable Paving: 100% of area | Green Roof: 100% (substrate ≥80mm) | Bioretention: 100% (infiltration-capable) | Soakaway: 100% | Tree Pit: ET credit | Swale: 50-100% | Filter Strip: 50-80%
Detention Basin (lined): 0% (attenuation only) | Retention Pond: 0% | Attenuation Tank: 0%
Compliance review and recommendations
Component contributions and compliance status
| Component Type | Area Served | Interception Credit | Volume Contribution | % of Total |
|---|