Retention Pond Calculator

CIRIA C753 §23: wet pond sizing for treatment, attenuation and biodiversity.

1
Site & Design
2
Calculate
3
Compliance
4
PDF Export
Project Information

Fields marked * are required

Catchment Parameters
from site plans
including soft landscape
ha
5-15mm typical, check local guidance
mm
water balance check
mm
EA May 2022 Climate Change Allowances Table 3 (surface-water peak rainfall intensity). These apply to peak-flow / attenuation storage for extreme events — they are carried by the attenuation volume you enter from Calculator 2 ("includes all return periods"). They are not applied to the water-quality treatment depth above, which sizes the permanent pool (a first-flush treatment volume per CIRIA C753 and so not climate-uplifted).
default 450mm for England
mm
if applicable, else 0
l/s
Design Requirements
These values come from Calculator 1 (Discharge Control) and Calculator 2 (Volume Estimation).
from Calculator 2, includes all return periods
from Calculator 1
l/s
Pond Geometry
typical 1-2m
m
shallow margin, ≤600mm
m
2:1 to 5:1
landscape design
bank stability
shallow planting zone
m
marginal vegetation zone
mm
above maximum water level
mm
Z = horizontal per 1m vertical
affects stability
sediment settling zone
Inlet & Outlet Design
1% AEP (100yr) overflow route
restricted discharge rate
Treatment Volume Calculation
CIRIA C753 Treatment Volume
Vt = (A_imp × d_rainfall) / 1000
Where:
• A_imp = Impervious area contributing to treatment (m²)
• d_rainfall = Design rainfall depth (mm)
• Vt = Treatment volume (m³)
Permanent Pool Volume
Pool Volume Based on Facility Type
V_pool = multiplier × Vt
• Retention Pond: multiplier = 4 × (CIRIA guidance for treatment & amenity)
• Constructed Wetland: multiplier = 3 × (shallower, greater surface area)
Surface Area & Dimensions
Required Surface Area for Permanent Pool
A_surface = V_pool / d_avg
Where:
• d_avg = Average depth ≈ 2/3 × max depth (reasonable approximation for trapezoidal ponds with shallow safety benching at 1:3 side slopes per CIRIA C753 §23.5; shallower ponds with steeper sides approach 1/2 × max depth; adjust if your geometry differs significantly)
Pond Dimensions from L:W Ratio
W = √(A_surface / ratio)
L = W × ratio
Residence Time
Hydraulic Residence Time for Treatment
t_res = (V_pool × 1000) / (Q_inflow × 3600)
Where:
• Q_inflow = Average inflow (l/s) = (rainfall × area) / seasonal factor
• t_res = Residence time (hours)
• Minimum acceptable: 24-72 hours for pollutant settling
Water Balance (Annual Average)
Annual Water Inflow & Outflow
Inflow (m³/yr) = (Annual rainfall × area / 1000) + (DWF × 86400 × 365 / 1000)
Outflow (m³/yr) = (Evaporation × pond_area / 1000) + seepage + discharge
Summary of Key Volumes
Treatment Volume
Permanent Pool
Attenuation Storage
Total Pond Volume
Surface Area
Residence Time
hours
Minimum 24h residence time recommended per CIRIA C753
Design Summary
Permanent Pool Volume
Treatment Volume
Attenuation Volume
Total Volume
Surface Area
Dimensions
L × W (m)
Max Depth
m
Freeboard
mm
Residence Time
hours
Forebay Volume
Design Cross-Section
Permanent Pool Water
Aquatic Bench Zone
Bank & Slope
Vegetation/Landscape
Compliance with Standards
Standard Requirement Design Value Status
Safety Design Notes
Amenity Design (S5)
  • Accessible pathways and viewing points (min 1.5m wide)
  • Landscaping integrated with site masterplan
  • Wildlife habitat enhancements (trees, shrubs)
  • Seating and rest areas (if space permits)
  • Interpretive signage planned
Biodiversity Design (S6)
  • Aquatic bench (2-3m wide, shallow margin)
  • Varied depth profile (shallow to deep zones)
  • Native marginal plants specified (reed-bed, willow)
  • Native submerged plants specified (pondweed)
  • Ramp or shallow entry for amphibians
  • Dead wood & brash piles for invertebrates
  • No pesticides or herbicides in maintenance
Maintenance & Access (S7)
  • Minimum 3m maintenance track around pond
  • Access for sediment removal equipment
  • Routine inspection schedule (6-12 monthly)
  • Annual vegetation management plan
  • Forebay sediment removal every 2-5 years
  • Main pool dredging every 10-20 years
Generate Professional Report
Export your design as a professional PDF report suitable for planning submissions, client review, or project documentation.
  • Project information & parameters
  • Design calculations with formulas
  • Volume summary & surface area
  • Compliance table (Standards S3-S7)
  • Design cross-section sketch
  • Water balance analysis
  • Safety design notes
Design Data